How to Write a Change Order (So You Actually Get Paid for Extra Work)

Short answer
A change order is a short written agreement, signed by you and the customer before the extra work starts, that changes the original contract. It should say what is changing, why, the added (or removed) cost, the effect on the schedule and payments, and have both signatures and a date. No signature, no extra work: a verbal "go ahead" is the most common reason contractors do extra work and never get paid for it.
What a change order is (and isn't)
A change order is an amendment to the contract you already signed. It's used when the scope, price or timeline changes after the job is agreed: the customer wants another room, picks a different finish, or you open a wall and find rot or water damage nobody could see.
It is not a new estimate for a new job, and it's not something you hand over after the work is done. The whole point is that the customer agrees to the price before you pick up a tool. Many contracts include a "changes in the work" clause that says how changes must be requested and approved, so read yours and follow it.
What every change order should include
Keep it to one page. It doesn't need legal language, but it does need these pieces:
- Your company name, phone and license number (if your state requires one).
- Customer name, job address and a reference to the original contract or estimate number.
- A change order number (CO #1, CO #2…) so nothing gets mixed up later.
- A clear description of the change, written so a stranger could understand it: what's added, removed or done differently.
- The reason: customer request, hidden condition, code requirement, design change.
- The price: materials, labor and your markup, or a credit if work is being removed.
- The new contract total (original + all approved change orders).
- The effect on the schedule: extra days and the new finish date.
- How and when it gets paid: with the next progress payment, upfront, or at the end.
- Signature and date from you and the customer (both owners if both signed the contract).
Step by step: how to write one on the job
This works for drywall, painting, flooring, remodeling, plumbing or any trade:
- 1Stop before doing the extra work. Tell the customer it's outside the original scope and you'll send the price in writing.
- 2Take photos of the condition or area. Photos explain hidden damage better than any paragraph.
- 3Measure and price it the same way you price an estimate: materials with waste, labor at your real cost per hour, overhead and profit.
- 4Write the description in plain words. "Replace 3 water-damaged sheets on the north wall of the basement and match the existing texture" beats "misc. repairs".
- 5Add the schedule impact, even if it's zero days. Customers argue less about time when they agreed to it in writing.
- 6Send it the same day and get the signature before starting. A signature on a phone counts in most places; check your state's rules if you're unsure.
- 7Keep a copy with the job file and add the amount to the next invoice so it doesn't get forgotten.
Example (numbers for illustration only)
These numbers are made up to show the math. Use your own costs and local prices.
Original job: hang and finish drywall in a basement for $6,000. While working, the homeowner asks to add a 10 × 12 storage room with a ceiling.
- Walls: 2 × (10 + 12) × 8 = 352 sq ft. Ceiling: 10 × 12 = 120 sq ft. Total: 472 sq ft.
- Example materials (sheets, screws, tape, mud, corner bead): $310.
- Example labor: 2 people × 7 hours × $38 real cost per hour = $532.
- Example overhead 15%: $126. Subtotal: $968.
- Example profit 20%: $194. Change order price: $1,162.
- New contract total: $6,000 + $1,162 = $7,162. Schedule: +1 day. Paid with the final payment.
What to do when the customer won't sign
Sometimes the homeowner says "just do it, we'll figure it out later." That's the moment to slow down, politely. Most payment fights start with extra work agreed by voice.
- Explain it's how you work on every job: it protects them too, because the price is fixed before you start.
- Offer options: do the change now at the written price, skip it, or do it later as a separate job.
- If it's a hidden condition that has to be fixed before you can continue (rot, a leak), document it with photos and send the change order immediately; don't keep building over it.
- If they still won't sign, don't do the extra work. "No change order, no change" is a common rule in the trades for a reason.
- If you already did extra work without a signature, send a written summary right away with photos and the price, and ask a local attorney about your options and lien deadlines in your state.
Common mistakes that cost contractors money
- Doing the work first and writing the change order later (or never).
- Vague descriptions like "extra work" or "additional repairs".
- Pricing the change at cost with no overhead or profit.
- Forgetting the schedule impact, then getting blamed for finishing late.
- Not updating the contract total, so the final invoice looks like a surprise.
- As a sub, doing extra work the GC asked for without getting a change order from the GC.
Doing it faster from your phone
The reason most contractors skip change orders isn't that they don't know better. It's that writing one feels like 30 minutes of paperwork while you're standing in a torn-open wall.
In Andamia you add the change order to the same job from your phone (in English or Spanish), with its own number, description and price. The customer gets a link to review and approve it on their phone, and once approved the amount is added to the job so it shows up when you invoice. Your crew can also report extra work from their app so it doesn't get lost. Whatever tool you use, the rule is the same: written, priced and signed before the work starts.
Common questions
Does a change order need to be signed before the work starts?
That's the safest practice and many contracts require it. If you do the work first, you may have a much harder time getting paid for it. Get the signature, then do the work.
Who can request a change order?
Either side. The customer can ask for a change, or the contractor can propose one, for example when hidden damage is found. Both have to agree on the scope, price and time for it to be a valid change order.
Should I add markup to a change order?
Yes. A change order is new work with its own overhead and risk. Price it like an estimate: materials, labor, overhead and profit.
Is a signature on a phone valid for a change order?
Electronic signatures are widely accepted in the US, but rules for home improvement contracts can vary by state. If you're unsure, check with your state's contractor board or a local attorney.
What's the difference between a change order and a new estimate?
A change order modifies a job that's already under contract and updates its total. A new estimate is for separate work that would have its own contract.